Research

Based on a real task from a production multi-agent workflow.

Command

agent-estimate estimate \
  "Audit cloud infrastructure providers for production deployment" \
  --type research

Output

Per-Task Estimates

Task Model Tier Agent Base PERT (O/M/P) Modifiers Effective Duration Human Equivalent
Audit cloud infrastructure providers for production deployment research S Claude 10m / 20m / 30m (E=20m) spec 1.00 x warm 1.00 x fit 1.00 = 1.00 20m 99m

Timeline Summary

Metric Value
Best case 27.1m
Expected case 38m
Worst case 48.9m
Human-speed equivalent 99m
Compression ratio 2.61x
Review overhead (per-task, pre-amortization) 15m

Agent Load Summary

Agent Task Count Total Work Estimated Cost
Claude 1 23m $0.55

No METR threshold warnings.

What actually happened

Metric Estimated Actual
Agent Claude Claude
Duration 38m expected ~15m
Outcome 12-section report, 7 providers evaluated, recommended hybrid deployment
Quality Q4 (strong)

The agent finished well under the estimate — research tasks with web access tend to run fast because agents scan documentation and pricing pages in parallel. The actual landed below even the best case (27m). This is typical for research: high variance, but the wins are dramatic.

Key takeaway

Research tasks have the highest human-multiplier range (3.0-6.0x) because pattern matching across large datasets is tedious for humans but routine for agents. Scanning 7 cloud providers' pricing, compliance, and feature matrices would take a human most of a workday. Use --type research to select the research estimation model — it uses a flat PERT curve with depth scaling instead of the tier-based coding model.